In pursuance of SEBI guidelines for appropriate adjustments for corporate actions vide their circular No. SEBI circular CIR/MRD/DP/122/2017 dated November 17, 2017, Exchange Notice No.20171221-20 dated December 21, 2017 and ICCL Notice No.20171117-40 dated November 17 2017, the members of the SLB segment Kindly take the note of the same:

In view of a corporate action in the below securities there shall be a foreclosure of transactions. The foreclosure schedule is as under:

Security Name

Type of Corporate action

Book Closure/Record date

Ex Date

Foreclosure Date

Shut Period

TECH MAHINDRA LTD.

AGM/DIVIDEND

25 July, 2020

23 July, 2020

23 July, 2020 (MCF” contracts)

22 July, 2020 to 25 July, 2020

PIRAMAL ENTERPRISES LTD.

AGM/DIVIDEND

18 July, 2020

16 July, 2020

16 July, 2020 (MCF” contracts)

15 July, 2020 to 18 July, 2020

HOUSING DEVELOPMENT FINANCE CORPORATION LTD.

AGM/DIVIDEND

13 July, 2020

09 July, 2020

09 July, 2020 (MCF” contracts)

08 July, 2020 to 13 July, 2020

BATA INDIA LTD.

AGM/DIVIDEND

29 July, 2020

27 July, 2020

27 July, 2020 (MCF” contracts)

24 July, 2020 to 29 July, 2020

MARUTI SUZUKI INDIA LTD.

AGM/DIVIDEND

15 August, 2020

13 August, 2020

13 August, 2020 (MCF” contracts)

12 August, 2020 to 15 August, 2020

GRANUALES INDIA LTD.

AGM/DIVIDEND

07 August, 2020

05 August, 2020

05 August, 2020 (MCF” contracts)

04 August, 2020 to 07 August, 2020

BOSCH LTD.

AGM/DIVIDEND

05 August, 2020

03 August, 2020

03 August, 2020 (MCF” contracts)

31 July, 2020 to 05 August, 2020

GODREJ INDUSTRIES LTD.

AGM

06 August, 2020

04 August, 2020

04 August, 2020 (MCF” contracts)

03 August, 2020 to 06 August, 2020 (MCF” contracts)

ADANI POWER LTD.

AGM

18 June, 2020

16 June, 2020

16 June, 2020 (MCF” contracts)

15 June, 2020 to 18 June, 2020 (MCF” contracts)

BRITANI INDUSTRIES LTD.

AGM

01 July, 2020

29 June, 2020

29 June, 2020 (MCF” contracts)

26 June, 2020 to 01 July, 2020 (MCF” contracts)

ADANI ENTERPRISES LTD.

AGM

19 June, 2020

17 June, 2020

17 June, 2020 (MCF” contracts)

16 June, 2020 to 19 June, 2020 (MCF” contracts)

JSW STEEEL LTD.

DIVIDEND

08 July, 2020

06 July, 2020

-

03 July, 2020 to 08 July, 2020

 

In case of foreclosure, lending fees for all open positions will be adjusted on a pro-rata basis. However, there will be no adjustment of lending fee on any transactions that are executed post the corporate action is announced and the market participants have been notified. Market participants should accordingly quote lending fee for a shorter transaction cycle.

All open positions in the above mentioned security shall be foreclosed on the foreclosure date (The reverse leg settlement will happen on the foreclosure date of the security)

For & on behalf of BSE Ltd,

Piyush Shelat

Manager - Trading Operations